TMV EXTEND AND RENOVATE FINGRID OYJ’S KONTIOLAHTI 110 KV SUBSTATION
15.05.2019
TMV will extend and renovate Fingrid Oyj’s Kontiolahti 110 kV substation
The delivery includes two 110 kV outdoor bays, new 110 kV busbar and replacing of the existing 110 kV primary equipment. Additionally delivery includes replacing of whole protection, automation and telecommunication systems.
The contract value is over 3 million euros and delivery will be ready November 2020.
Additional information:
TMV Jukka Roponen +358 45 7731 2542 jukka.roponen@tmvservice.fi